Hiba Academy - Exterior

Hiba Academy Bay Area

ClientHiba Academy Bay Area
ExpertiseEducation K-12 | Adaptive Reuse
LocationSan Francisco Bay Area, California, USA

Converting a fully-occupied commercial building to a school — a B-to-E occupancy change — while holding budget and delivering in time for a fall opening.

Photos
Drawings
The story

From acquisition to opening day

The client had identified a commercial building well suited to their program, but it carried a business occupancy classification — converting it to educational use meant satisfying a stricter code path end to end (egress, fire and life safety, accessibility, and seismic) before a single classroom could open. We began with a full existing-conditions and code assessment before the client committed, mapping exactly what the B-to-E conversion would require, then sequenced permitting with the local building department early so approvals tracked the construction schedule instead of trailing it. The campus opens on schedule this fall as a fully permitted educational occupancy — the definitive proof point for clients weighing a similar acquisition: the code and occupancy risk is real, and it's solvable with the right assessment up front.

01 Assess02 Envision03 Permit04 Transform
Testimonial

“They opened our campus on schedule, inside a building we weren't sure we could legally use as a school — and gave our community a real story to tell.”

— Head of School

Before / after
Before — business occupancy
Hiba Academy - Existing Building
After — educational occupancy
Hiba Academy - Exterior

Project details

Size60,000 SF
ConversionB → E occupancy
ScheduleOpening fall 2026
BudgetHeld to plan
ApprovalsFull change of use cleared
SustainabilityEmbodied carbon retained
Back to All Work

Considering a similar conversion?

Every occupancy change starts with an honest feasibility assessment — before you commit.

Start a conversation